Valid 74-344 Dumps shared by ExamDiscuss.com for Helping Passing 74-344 Exam! ExamDiscuss.com now offer the newest 74-344 exam dumps, the ExamDiscuss.com 74-344 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 74-344 dumps with Test Engine here:
You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule. You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks. You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks. What should you do next?