You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
Review the project data after the project managers create the projects.

Send the projects back to the project managers if you find incorrect data so that they can make the

appropriate corrections.
Repeat the data verification process unless the data does not have any errors.

Publish a project only when all of its data is correctly completed.

What should you do?