You are a project manager for an organization that uses Project Server 2013 with Project Professional 2013. The stakeholders on your project want to easily view the issues related to tasks on your project schedule from within Project Center. You need to allow the stakeholders to view the related issues. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: B,D
Explanation/Reference: D: . Navigate to the Project Site and create your issue. 2. Open the schedule in PWA. 3. Select the task you want the issue to be linked to. 4. On the 'Options' ribbon, click on 'Related Items': 5. Next to 'related items', click 'Add Related Item'. 6. Double Click on 'Issues 7. Double click on the issue you want to be linked.