You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has experience with Microsoft SharePoint task lists. The free form tracking method has been selected in Project Server
2013.
You plan to create task assignments.
You need to implement update procedures that meet the following requirements:
Resources need to be able to report on a task when it is completed.

Resources should NOT have the ability to report on partially completed tasks.

Resources should be able to easily and quickly update project tasks.

Which two update procedures should you implement? (Each correct answer presents part of the solution.
Choose two.)