DRAG DROP
You are a project manager for an organization that uses Project Server 2013.
You check out a project for editing in Project Professional 2013 and discover that one resource is overallocated across three projects.
You need to determine the cause of the overallocation by using the Team Planner view to resolve the issue.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.) Select and Place:

Correct Answer:

Explanation/Reference:
Box 1: Double-click Other projects and commitments
Box 2: Open the additional project(s) that the resource is assigned to.
Box 3: Display the Team planner view and locate the tasks for the overallocated resources.
Box 4: On the Team Planner view, click Prevent Overallocations
Note:
* Box 3

* Box 4: