You manage a project and use Microsoft Project to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their availability. The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved. You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task. What should you do?