You are managing a project by using Microsoft Project. The project has a baseline that was set after the schedule was approved. The project has a work budget. The project is currently 50 percent complete. You are using a standard report, with no customization.
You need to create a report that graphically compares baseline with actual work completed.
Which two actions will achieve the goal? Each correct answer presents a complete solution?
Correct Answer: B,D
Explanation/Reference:
References: