You are a project manager who uses Microsoft Project.
You work on a software development project, and the Project Management Office (PMO) requires you to enter project costs associated with all work completed on your project.
You receive invoices for 55,000 for software licenses and $150 for supplies. Software licensing costs are associated with Task A: Obtain Software License. Supply costs are associated with Task H: Project Management Administration.
You need to enter the costs into your project schedule.
Which two steps should you perform? (Each correct answer presents part of the solution. Choose two.)