Question 34/70

You are a project manager who uses Microsoft Project, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable.
Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.
You need to create a formula to calculate the total number of deliverables that are completed.
Which two steps should you perform? (Each correct answer presents part of the solution. Choose two.)

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (70q)
Question 1: You are a project manager who uses Microsoft Project. You ma...
Question 2: Your organization uses Microsoft Project. You are setting up...
Question 3: This question requires that you evaluate the underlined text...
Question 4: This question requires that you evaluate the underlined text...
Question 5: You are a project manager, and your organization uses Micros...
Question 6: Your company uses Microsoft Project. You are building a sche...
Question 7: Your company uses Microsoft Project, and you are setting up ...
Question 8: You are managing a project by using Microsoft Project. Your ...
Question 9: You manage a project for an organization that uses Microsoft...
Question 10: You are using Microsoft Project. Management wants to see an ...
Question 11: You are a project manager for a company that uses Microsoft ...
Question 12: You manage a project by using Microsoft Project. The Indicat...
Question 13: You are a project manager in an organization that uses Micro...
Question 14: While creating a schedule with Microsoft Project, you notice...
Question 15: You are creating a schedule by using Microsoft Project. You ...
Question 16: You are a project manager for a company that uses baselines ...
Question 17: You are reviewing a schedule in Microsoft Project. Your orga...
Question 18: While scheduling with Microsoft Project you notice that ther...
Question 19: Your company uses Microsoft Project. You are scheduling two ...
Question 20: You are a project manager who uses Microsoft Project. You wo...
Question 21: You are a program manager. Your project managers use Microso...
Question 22: This question requires that you evaluate the underlined text...
Question 23: You are tracking a project schedule by using Microsoft Proje...
Question 24: You are a project manager who uses Microsoft Project. You ma...
Question 25: You work as a project manager for a construction company tha...
Question 26: You are a project manager who uses Microsoft Project. Your m...
Question 27: Your company uses Microsoft Project. You have several projec...
Question 28: You create a new schedule by using Microsoft Project. All ca...
Question 29: You are a project manager who uses Microsoft Project. You ha...
Question 30: You use Microsoft Project to manage a project for your organ...
Question 31: You are a project manager who uses Microsoft Project. You ha...
Question 32: Your project managers manage several projects using Microsof...
Question 33: You are a project manager who uses Microsoft Project. You ar...
Question 34: You are a project manager who uses Microsoft Project, and yo...
Question 35: You are a project manager for a large telecommunications com...
Question 36: You are using Microsoft Project. Three years ago, you succes...
Question 37: You use Microsoft Project to manage a project schedule which...
Question 38: You are a project manager who uses Microsoft Project. Your o...
Question 39: You update a schedule that you are managing by using Microso...
Question 40: You are a program manager who uses Microsoft Project. You ma...
Question 41: You are a project manager and have built a project plan by u...
Question 42: You are managing a project by using Microsoft Project. The p...
Question 43: Your organization uses Microsoft Project. A senior stakehold...
Question 44: You are a project manager who uses Microsoft Project. A seni...
Question 45: You create a new project by using Microsoft Project. You hav...
Question 46: You are a project manager who uses Microsoft Project. You wo...
Question 47: You are a project manager who uses Microsoft Project. When v...
Question 48: You are a project manager who uses Microsoft Project. You ma...
Question 49: You are a program manager for a complex software development...
Question 50: You manage a project schedule by using Microsoft Project. Yo...
Question 51: You are an independent project manager who uses Microsoft Pr...
Question 52: You are a project manager who uses Microsoft Project. You ne...
Question 53: You are a project manager who uses Microsoft Project. You ar...
Question 54: You are a manager for an organization that uses Microsoft Pr...
Question 55: Your organization uses Microsoft Project and records actual ...
Question 56: You are a project manager who uses Microsoft Project. All re...
Question 57: You are a project manager who uses Microsoft Project. You re...
Question 58: Your company uses Microsoft Project. You are a program manag...
Question 59: You manage a project by using Microsoft Project. The work va...
Question 60: You are a project manager who uses Microsoft Project. You ar...
Question 61: You manage a project and use Microsoft Project to track your...
Question 62: You are managing a project schedule by using Microsoft Proje...
Question 63: You are a project manager who uses Microsoft Project. A coll...
Question 64: Your organization uses Microsoft Project. A senior stakehold...
Question 65: Your organization uses Microsoft Project. You are finalizing...
Question 66: A company is open for business Monday through Friday, 7:30 A...
Question 67: You are a project manager, and you use Microsoft Project for...
Question 68: You manage a project by using Microsoft Project. Your projec...
Question 69: You are a project manager who uses Microsoft Project. Two of...
Question 70: You are using Microsoft Project. You want the ability to see...