You are a project manager who uses Microsoft Project. Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Microsoft Project. The standard Microsoft Project report views named Late Tasks and Milestone Report already have all the information required for the new model. You are assigned to consolidate the information from these two reports into a dashboard view named Status Report Model. Your organization wants to keep the same format, colors, and layout. You need to implement this solution. What should you do?