You are a program manager for a complex software development project. You use Microsoft Project to manage your project. Your resources work on many different projects across the program, and you need to resolve resource over allocations. Your project team uses a resource pool to manage resources.
Resource1 has been assigned to assist on a project that is on the critical path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the month of November. Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to.
Using resource leveling in Microsoft Project, you need to resolve the over allocation for Resource1 for the month of November only.
What should you do?