Which of the following is the ULTIMATE objective of utilizing key control indicators (KCIs) in the risk management process?
Correct Answer: D
Key control indicators (KCIs) are metrics that measure the performance of a control in reducing the causes, consequences, or likelihood of a risk. They help to evaluate the adequacy and efficiency of the internal control environment, which is the set of policies, procedures, and practices that support the achievement of organizational objectives and the management of risks. By monitoring KCIs, organizations can identify and address any gaps or weaknesses in their internal controls and ensure that they are operating as intended. References *ISACA CRISC Review Manual, 7th Edition, Domain 3: Risk Response, Section 3.2.2: Control Design and Implementation *KRI Framework for Operational Risk Management | Workiva *What is the difference between key risk indicators and key control indicators?