Which of the following is the PRIMARY reason for sharing risk assessment reports with senior stakeholders?
Correct Answer: A
The primary reason for sharing risk assessment reports with senior stakeholders is to support decision-making for risk response. Risk assessment reports are documents that summarize the results of the risk assessment process, such as the risk sources, causes, impacts, likelihood, and levels. Risk assessment reports also provide recommendations for risk response options, such as avoiding, reducing, transferring, or accepting the risk.
Sharing risk assessment reports with senior stakeholders helps to inform them of the current risk situation, and to solicit their input, feedback, or approval for the risk response actions. The other options are not the primary reason for sharing risk assessment reports, although they may be secondary reasons or outcomes. References = Risk and Information Systems Control Study Manual, Chapter 4, Section 4.2.1, page
4-13.