During which of the following quality process steps are the roles and responsibilities of project team members finalized and the team established?
Correct Answer: A
Quality planningis the phase where teams define quality standards, finalize roles and responsibilities, and assemble the project team. This step establishes accountability frameworks and prepares the team to meet quality objectives. The IASP SPP curriculum emphasizes quality planning as foundational for ensuring that subsequent control and improvement activities are effective and aligned with strategy. Quality control, assurance, and continuous improvement follow, focusing on monitoring, compliance, and enhancements.