During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
Correct Answer: B
A business case documents the rationale and expected benefits of a project. This document is essential for project approval and aligns with CompTIA Project+ guidance on project initiation and planning.