A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?
Correct Answer: B
Evaluating the impact to baselines (such as schedule and budget) helps determine the delay's effect on the project. This aligns with CompTIA Project+ guidance on project control, which emphasizes analyzing impacts before taking corrective actions.