As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
Correct Answer: B
An Ishikawa diagram, also known as a fishbone diagram, is a tool used to identify and analyze the root causes of a particular problem. CompTIA Project+ references this tool as essential for quality management and problem-solving.