A project manager is monitoring the performance of the development team and creates the following view: Planned Task Completion Actual Task Completion Which of the following describes the status of the project?
Correct Answer: B
Comprehensive and Detailed Step-by-Step If the actual task completion is lagging behind the planned task completion, the project is behind schedule. This indicates that the project is not progressing as planned and may require corrective actions such as resource reallocation or schedule adjustments. Reference: CompTIA Project+ PK0-005 Official Study Guide, Chapter 7: Monitoring Project Performance