A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
Correct Answer: B
A downtime window schedule specifies a timeframe during which systems can be taken offline or changed without affecting business operations. CompTIA Project+ includes this as part of deployment planning to ensure minimal disruption to stakeholders.