During quality analysis, different team members are identifying multiple constraints. Which of the following
tools should the project manager adopt first to help track and prioritize a resolution?
Correct Answer: A
An issue log is a tool that records and tracks any issues that arise during the project. It helps the project
manager to identify, prioritize, assign, monitor, and resolve the issues in a timely manner. An issue log can
also include information such as the issue description, impact, status, owner, and resolution date1. An issue log
is different from a defect log, which records and tracks the defects or errors in the project deliverables. A risk
register is a tool that records and tracks the potential risks that may affect the project objectives. A change log
is a tool that records and tracks the changes that are made to the project scope, schedule, budget, or quality2.