Valid PK0-005 Dumps shared by ExamDiscuss.com for Helping Passing PK0-005 Exam! ExamDiscuss.com now offer the newest PK0-005 exam dumps, the ExamDiscuss.com PK0-005 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-005 dumps with Test Engine here:
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
Correct Answer: A
A time and materials contract is a type of contract where the buyer pays the seller for the actual time and materials used during the project. This type of contract is suitable when the scope of work is uncertain or likely to change, and the vendor cannot provide accurate estimates. The document also specifies the resources involved and the rates the vendor will charge for the work12.