A project manager was just assigned to a new project. Which of the following activities should the project
manager undertake after accepting the project? (Select TWO).
Correct Answer: E,F
Review the resource pool and review the project objectives are activities that the project manager should
undertake after accepting a new project. Reviewing the resource pool involves identifying and evaluating the
availability, skills, and competencies of the human and material resources that are needed for the project.
Reviewing the project objectives involves understanding and clarifying the expected outcomes and benefits of
the project and how they align with the organizational strategy and stakeholder expectations. These activities
can help to plan and execute the project effectively and efficiently.