A project manager is organizing and running a project closure meeting. Which of the following best describes
the objective of this meeting?
Correct Answer: B
A project closure meeting is a formal gathering held at the end of a project timeline. Its chief purpose is to
evaluate the project's performance, identify and discuss the achieved outcomes, successes, and challenges, and
confirm that all predefined tasks and objectives have been completed successfully1. The project closure
meeting also involves obtaining project sign-off from all necessary parties, such as the project sponsor, the
client, the stakeholders, and the team members. Project sign-off is the official approval that the project has met
the agreed-upon criteria and quality standards, and that the project is formally closed2.