A project coordinator has started a new project and is reviewing the following characteristics provided by the
customer:
* Two developers
* High uncertainty about existing systems
* Risk of frequent requirement changes
* Tight deadlines
Which of the following project methodologies would be best to use in this situation?
Correct Answer: B
This answer is based on the best practice of choosing a project management methodology that suits the project
characteristics and environment12. Scrum is an agile framework that is designed to handle complex and
uncertain projects with frequent changes and tight deadlines34. Scrum involves a small, cross-functional team
that works in short iterations called sprints, delivering incremental and potentially shippable products at the
end of each sprint5. Scrum also allows for continuous feedback and improvement through daily stand-up
meetings, sprint reviews, and retrospectives6. Scrum is suitable for this project because it can accommodate
the high uncertainty, the risk of requirement changes, and the tight deadlines, while also enabling the two
developers to collaborate effectively and deliver value to the customer. References = CompTIA Project+
Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, Project Management
Methodologies Comparison (11 PM Methods)6, Project Management Methodologies: 12 Best Frameworks
[2023]7, What is Scrum?5, Scrum Methodology: The Ultimate Guide6