A company decides to adopt a total quality system and has started the process by developing quality policies. Rank in order, from first to last, the rest of the steps that need to be performed to implement this system. 1.Audit the system 2.Determine system requirements 3.Develop a measurement system 4.Perform continuous improvement activities H Calculator
Correct Answer: B
To implement a total quality system, the steps should be performed in the following order: * Determine system requirements (2) * Develop a measurement system (3) * Audit the system (1) * Perform continuous improvement activities (4) This sequence ensures that the system's needs are identified first, followed by the establishment of metrics to measure performance. Auditing verifies compliance and effectiveness, and continuous improvement ensures ongoing enhancement of the quality system.