When measuring progress using tasks that lack readily definable intermediate milestones and level of effort required is difficult to measure, the best methods to use is:
Correct Answer: B
When progress measurement is difficult due to the lack of intermediate milestones and challenging-to-define effort levels, Weighted or Equivalent Units is an effective method. Key Points: Weighted or Equivalent Units: This method involves assigning a percentage or weight to different parts of a task based on their relative effort or importance. It allows for more granular and realistic progress tracking when clear milestones are absent. Other Methods: Start/Finish: Suitable for tasks with clear start and end points but may oversimplify progress measurement. Incremental Milestones: Effective when intermediate steps are well-defined. Cost Ratio: Focuses on the cost expended versus the planned cost, which might not reflect actual physical progress. Conclusion: The correct answer is B. Weighted or equivalent units because this method is specifically designed to handle complex tasks where other progress measurement methods might fall short.