A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. When analyzing a precedence diagram schedule, the "backward pass"
Correct Answer: A
In project scheduling, performing a backward pass through a precedence diagram allows the project manager to calculate the total float for each activity. The backward pass starts from the project's end date and works backward to determine the latest possible start and finish times for each activity without delaying the project. This calculation is essential for identifying critical path activities and understanding where there is flexibility in the schedule (i.e., float) for non-critical tasks. Top of Form Bottom of Form