Valid CCP Dumps shared by ExamDiscuss.com for Helping Passing CCP Exam! ExamDiscuss.com now offer the newest CCP exam dumps, the ExamDiscuss.com CCP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CCP dumps with Test Engine here:
The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. In the A relationship, the subcontractor might use an unbalance bid to:
Correct Answer: A
Given Scenario: The question is asking what a subcontractor might achieve by using an unbalanced bid in the structure shown as Plan A. An unbalanced bid is a bidding strategy where the subcontractor assigns higher costs to early stages of work. This allows the subcontractor to receive more money early in the project, reducing their financial risk and providing better cash flow.