A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:
Correct Answer: A
Given Scenario: The difference between the latest allowable end time and the earliest allowable end time of a schedule activity is inquired. This difference is referred to as Total Slack or Total Float. It indicates the amount of time that a project task can be delayed without affecting the overall project schedule.