Valid LEED-AP-BD-C Dumps shared by ExamDiscuss.com for Helping Passing LEED-AP-BD-C Exam! ExamDiscuss.com now offer the newest LEED-AP-BD-C exam dumps, the ExamDiscuss.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-AP-BD-C dumps with Test Engine here:
The required minimum scope of analysis for a product-specific declaration that contributes toward Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations, Option 1. Environmental Product Declaration is
Correct Answer: B
The minimum scope of analysis for a product-specific declaration is cradle-to-gate, which means from raw material extraction to the factory gate. This option requires the use of at least 20 different permanently installed products sourced from at least five different manufacturers that have product-specific declarations. References: *LEED v4 BD+C Reference Guide, page 5441 *LEED v4.1 BD+C MRc2 Building Product Disclosure and Optimization (BDPO) EPD credit2