Valid LEED-AP-BD-C Dumps shared by ExamDiscuss.com for Helping Passing LEED-AP-BD-C Exam! ExamDiscuss.com now offer the newest LEED-AP-BD-C exam dumps, the ExamDiscuss.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-AP-BD-C dumps with Test Engine here:
The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
Correct Answer: D
According to the LEED v4 Reference Guide for Building Design and Construction, Option 2 of the Sourcing of Raw Materials credit requires using products that meet at least one of the responsible extraction criteria for at least 25%, by cost, of the total value of permanently installed building products in the project1. Therefore, for a project with a material cost of $100,000, the minimum material value needed to achieve this option is 25% of $100,000, which is $25,000.