Valid Service-Cloud-Consultant Dumps shared by ExamDiscuss.com for Helping Passing Service-Cloud-Consultant Exam! ExamDiscuss.com now offer the newest Service-Cloud-Consultant exam dumps, the ExamDiscuss.com Service-Cloud-Consultant exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com Service-Cloud-Consultant dumps with Test Engine here:
A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints. What is the first step the consultant should take to address the issue?
Correct Answer: B
When additional requirements are discovered that impact the project's timeline and budget, preparing a change order to account for these requirements is the first step. This involves adjusting the project scope, timeline, and budget to accommodate the new requirements, ensuring that all stakeholders are aligned and informed about the changes and implications for the project's delivery.
Recent Comments (The most recent comments are at the top.)
Salesforce Premi - Jun 13, 2025
Answer is C :
When additional requirements are discovered early in a project that has a fixed budget and timeline, the consultant's first step should be to document the gap in requirements and discuss the potential impacts on schedule and budget with the project team. This approach ensures that all stakeholders are aware of the changes and can collaboratively decide on the best course of action.
Key Considerations:
Scope Management:Clearly defining and managing project scope is crucial. Any changes to the scope should be carefully evaluated for their impact on time and cost.
Stakeholder Communication:Engaging with stakeholders to discuss the implications of additional requirements helps in setting realistic expectations and making informed decisions.
Change Control Process:Before implementing any changes, it's essential to follow a formal change control process, which includes documenting the change, assessing its impact, and obtaining necessary approvals.
By taking these steps, the consultant ensures that the project remains aligned with its objectives and constraints, and any deviations are managed in a controlled and transparent manner....
Recent Comments (The most recent comments are at the top.)
Answer is C :
When additional requirements are discovered early in a project that has a fixed budget and timeline, the consultant's first step should be to document the gap in requirements and discuss the potential impacts on schedule and budget with the project team. This approach ensures that all stakeholders are aware of the changes and can collaboratively decide on the best course of action.
Key Considerations:
Scope Management:Clearly defining and managing project scope is crucial. Any changes to the scope should be carefully evaluated for their impact on time and cost.
Stakeholder Communication:Engaging with stakeholders to discuss the implications of additional requirements helps in setting realistic expectations and making informed decisions.
Change Control Process:Before implementing any changes, it's essential to follow a formal change control process, which includes documenting the change, assessing its impact, and obtaining necessary approvals.
By taking these steps, the consultant ensures that the project remains aligned with its objectives and constraints, and any deviations are managed in a controlled and transparent manner....
C seem more plausible