Valid C_TS412_2021 Dumps shared by ExamDiscuss.com for Helping Passing C_TS412_2021 Exam! ExamDiscuss.com now offer the newest C_TS412_2021 exam dumps, the ExamDiscuss.com C_TS412_2021 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS412_2021 dumps with Test Engine here:
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
Correct Answer: C
To analyze the capacity requirements of their project, you can recommend using the extended capacity evaluation report. The extended capacity evaluation report displays capacity requirements and availability for work centers or resources over a period of time. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual capacity requirements or availability situations by choosing drilldown functions. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html