Valid C_TS412_2021 Dumps shared by ExamDiscuss.com for Helping Passing C_TS412_2021 Exam! ExamDiscuss.com now offer the newest C_TS412_2021 exam dumps, the ExamDiscuss.com C_TS412_2021 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS412_2021 dumps with Test Engine here:
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
Correct Answer: A,C,D
To generate project stock reservations for a component assigned to a network activity, the following prerequisites must be met: The network activity must be assigned to a WBS element that is relevant for project stock management. The material master of the component must have a procurement type that allows project stock management (such as E, F, or X) and an individual/collective requirements indicator that allows individual requirements (such as 2 or 4). The project definition must have the Project Stock indicator set to either non-valuated or valuated project stock. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002