Valid C_TS412_2021 Dumps shared by ExamDiscuss.com for Helping Passing C_TS412_2021 Exam! ExamDiscuss.com now offer the newest C_TS412_2021 exam dumps, the ExamDiscuss.com C_TS412_2021 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS412_2021 dumps with Test Engine here:
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget
Correct Answer: D
Availability control is a function that can be used to check assigned values against the current budget for WBS elements within your project. Availability control is a process that monitors whether budget overruns occur in your project and issues warnings or error messages if predefined tolerance limits are exceeded. You can activate availability control for individual WBS elements or for entire projects and define different tolerance limits for different types of costs or revenues. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html