Valid C_TS412_2021 Dumps shared by ExamDiscuss.com for Helping Passing C_TS412_2021 Exam! ExamDiscuss.com now offer the newest C_TS412_2021 exam dumps, the ExamDiscuss.com C_TS412_2021 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS412_2021 dumps with Test Engine here:
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?
Correct Answer: A
To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you can ensure that the dates of the maintenance orders are synchronized with the dates of the WBS elements and the network activities. You can also use overall network scheduling to schedule several networks and maintenance orders together. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1