Your role in the project includes helping to resolve problems; making recommendations regarding priorities; accelerating activities to meet the target schedule; promoting communications among project team members; and helping management monitor the project's progress on a regular basis. Most of the people working on your project are scientists or technical experts. You are working in which of the following types of organizational structures?
Correct Answer: C
Section: Mix Questions Explanation: A variation of the weak matrix organizational structure, the project expeditor has no formal authority to make or enforce decisions. Nonetheless, the project expeditor must be able to persuade those in authority to maintain the project's visibility so that resources will be allocated as needed to meet the project's schedule, budget, and quality constraints. This approach is considered to be effective in high-technology and research and development environments.