The Project Manager is working with the customer to gain formal acceptance on the documentation deliverables for a software project. The customer is saying that the deliverables are unusable in their present form as they don?t align with the project requirements. Upon reviewing documentation, the customer tells the Project Manager that the requirements are not accurate, to meet the needs for which the project was undertaken. Which of the following will help fix this problem?