Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
Project managers spend a great deal of time communicating with the team, the stakeholders, the client, and the sponsor. One can easily see the challenges involved, especially if one team member must communicate a technical concept to another team member in a different country. The first step in this process is to______________
Correct Answer: A
Explanation/Reference: Explanation: As the first step in the basic communication model, it is essential to translate thoughts or ideas into a language that is understood by others. Then, the message is sent using various technologies, and the receiver decodes it or translates it back into meaningful thoughts or ideas.