Question 89/231

You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
Project Actual Earned Planned week costs value value 1 $65,000 $61,000 $67,000 2 $85,000 $79,000 $89,000 3 $100,000 $102,000 $110,000 4 $125,000 $124,000 $121,000 5 $135,000 $133,000 $139,000 6 $125,000 $120,000 $131,000

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (231q)
Question 1: During a review meeting, the project manager realizes that s...
Question 2: The Project Management Process Group in which performance is...
1 commentQuestion 3: During a project review meeting, stakeholder A points out th...
Question 4: During the retrospective ceremony, the agile team is talking...
Question 5: A project has been long and difficult. The team is relieved ...
Question 6: A comprehensive definition of scope management would be:...
Question 7: The work that must be done in order to deliver a product wit...
Question 8: The process of identifying specific actions to be performed ...
Question 9: The ISO 9000 standards provide______________...
Question 10: An issue log is an input to which Project Human Resource Man...
Question 11: Drag the organizational characteristics on the left to the c...
Question 12: You are in the process of purchasing 67 desktop computers, m...
Question 13: During implementation of the delivery as defined in the proj...
Question 14: During which phase of the project lifecycle is the level of ...
Question 15: A project manager is receiving conflicting requirements from...
Question 16: You are the project manager on a project to improve traffic ...
Question 17: A project manager has been assigned to a new project. During...
Question 18: A prefects key stakeholder resigns and a new one is selected...
Question 19: During the daily standup meeting that is assessing progress ...
1 commentQuestion 20: A project is on its sixth iteration out of seven. Select the...
1 commentQuestion 21: Based on the following table, what is the total float for ac...
Question 22: Conditions that are not under the control of the project tea...
Question 23: You are a contract project manager within an information tec...
Question 24: There is a project with CPI = 0.81 and TCPI = 1.00001; this ...
Question 25: A project manager is initiating a highly controversial proje...
Question 26: Assume that your actual costs are $1,000; your planned value...
Question 27: The Project Manager is working with the customer to gain for...
Question 28: When comparing the cost of competing projects, which of the ...
Question 29: You have been hired as a project manager for a small local b...
Question 30: A project manager in a large government agency is implementi...
Question 31: A large corporation completed a corporate social responsibil...
Question 32: After numerous meetings, the project manager was unable to o...
Question 33: The project manager has recently received funding approval f...
Question 34: Which of the following project communication management proc...
Question 35: You are in the process of defining how to plan and execute t...
Question 36: Management decision-making includes:...
Question 37: A project manager at a company is considering a high-perform...
Question 38: A construction project to build a fish hatchery is in execut...
Question 39: Which is not an activity included in the Integrated change c...
Question 40: Units of measure, level of precision, level of accuracy, con...
Question 41: Drag the characteristics of the stage on the left to the cor...
Question 42: Risk mitigation involves______________...
Question 43: A project manager learns that the team can implement a minor...
Question 44: The Plan Stakeholder Management process belongs to which Pro...
Question 45: 80% of the problems are found in 20% of the work is a concep...
Question 46: In the phase sequence defined by project life cycles, a phas...
Question 47: A project must be simultaneously implemented in two countrie...
Question 48: A series of consecutive points on the same side of the avera...
Question 49: The ISO 9000 standards provide______________...
Question 50: The Project Manager is in the process of planning the projec...
Question 51: A team receives outsourced deliverables and determines that ...
Question 52: An intern is replacing a critical resource midway through a ...
Question 53: A project manager has been asked to participate in the procu...
Question 54: In which of the following types of organizational structures...
Question 55: The most common communication problem during negotiations is...
Question 56: In your software project, you have a programmer who constant...
Question 57: Drag the interpersonal skill on the left to the correct scen...
Question 58: An employee approaches you and asks to tell you something in...
Question 59: Which of the following is not a scope management process?...
Question 60: A project manager is assigned to a new project. Many of the ...
Question 61: Integrated change control includes the following activities ...
Question 62: Requirements for formal contract acceptance and closure usua...
Question 63: Which is the Estimate Costs technique used most frequently i...
Question 64: Your stakeholders have asked for an analysis of the cost ris...
Question 65: A project was assessed and the following Earned value data h...
Question 66: An example of coercive power would be:...
Question 67: The stakeholders on a new compliance project request a deliv...
Question 68: You are a contract project manager for a wholesale flower di...
Question 69: Which of the following factors is lowest at the start of the...
1 commentQuestion 70: A project manager notices an unusually high rate of risks, b...
Question 71: During a project's execution phase, the project manager rece...
Question 72: Which of the following is a tool for analyzing a design, det...
Question 73: Which of the following statement are false?...
Question 74: A project is sponsored by the client's chief technology offi...
Question 75: Which of the following is an input of the Define Activities ...
Question 76: (Exhibit) Based on the project scheduled, how much float is ...
Question 77: In what knowledge area does Activity Resource Estimating occ...
Question 78: Which quality management and control tool is useful in visua...
Question 79: Early in a project, a team member failed to effectively comm...
Question 80: Which of the following is true regarding product scope descr...
Question 81: You are the project manager responsible for constructing new...
Question 82: A vendor who supplied material that failed to meet a technic...
Question 83: While browsing a local archive, a new project manager finds ...
Question 84: Which of the following is CORRECT about quality improvements...
Question 85: The lowest level normally depicted in a work breakdown struc...
Question 86: Your selection committee is debating between two projects. P...
Question 87: The profitability and technical data studies are provided in...
Question 88: Assume you are beginning your project to develop a series of...
Question 89: You monitored figures on cost and planned/earned value for e...
Question 90: Your project has been under way for some time, but indicator...
Question 91: You are managing a software development project. One of your...
Question 92: A number of organizational process assets are useful as inpu...
1 commentQuestion 93: At the end of project execution, a project manager has retai...
Question 94: Working on your project management training curricula projec...
Question 95: Which type of management focuses on ensuring that projects a...
Question 96: In a project management team meeting, one of the team member...
Question 97: Alberto is the project manager of a software implementation ...
Question 98: Which statement describes best the purpose of brainstorming ...
Question 99: A project manager developed the scope management plan for a ...
Question 100: Which of the following is true about pure risk?...
Question 101: A project manager assumes a three-year, multiphase project w...
Question 102: Calculate the standard deviation for the following: Pessimis...
Question 103: Which type of analysis is used to develop the communications...
Question 104: A team has been working together for several months and has ...
Question 105: Each project can benefit from stakeholder involvement; howev...
1 commentQuestion 106: During the next monthly meeting, a project manager wants to ...
Question 107: At what stage of a project does the development of a cohesiv...
Question 108: Which process involves the creation of a document that provi...
Question 109: Tom is a project manager on an industrial design project. He...
Question 110: According to a new product development process, the marketin...
Question 111: You realize that on projects, some stakeholders will not be ...
Question 112: Obtaining information from prospective sellers on how projec...
Question 113: A project plan generally includes the following:...
Question 114: A project manager discusses a project's status with the cust...
Question 115: You are managing a project with an EV of $15,000, PV of $12,...
Question 116: During a project's planning session, the project team discus...
Question 117: The scope baseline/project charter is prepared by the:...
Question 118: The end point of a project phase can be referred to as:...
Question 119: The purpose of a numeric scale in risk management is to_____...
Question 120: The process of monitoring the status of the project to updat...
Question 121: During a project to create an organizational business plan, ...
Question 122: A project is delayed. The project manager added extra resour...
Question 123: Drag the interpersonal skill on the left to the correct scen...
Question 124: Which of the following are valid ways to breakdown the work ...
Question 125: You are currently in the process of prioritizing risks by th...
Question 126: You are in the process of controlling changes to the project...
Question 127: You have been assigned to a project to build a large 30-stor...
Question 128: Labor, materials, equipment, and supplies are examples of:...
Question 129: The project will be using a company to provide the technicia...
Question 130: After finishing the planning phase of a project, but before ...
Question 131: In Project Cost Management, which input is exclusive to the ...
Question 132: Create Procurement document is done in _______....
1 commentQuestion 133: In response to a delay, a project manager adds new resource ...
Question 134: You have a conflict on your team but have enough time to res...
Question 135: I luting project execution, a project manager identifies a m...
Question 136: Mark is a project manager working on a compliance project in...
Question 137: During the executing phase, a project manager is reviewing t...
Question 138: At the end of a meeting a functional manager takes the proje...
Question 139: A lessons learned is BEST completed by:...
Question 140: Respect is...
Question 141: Participative Management:
Question 142: Analogous Estimate Costs is _________....
Question 143: Which of the following is an input to Direct and Manage Proj...
Question 144: In your project, if earned value (EV) is larger than planned...
Question 145: The risk management plan is a subset of the project manageme...
Question 146: Project managers spend a great deal of time communicating wi...
Question 147: On your project, you need to assign costs to the time period...
Question 148: In your last project status meeting, you had 15 team members...
Question 149: You can use various estimating approaches to determine activ...
Question 150: The Project Manager has some issues on the team between two ...
Question 151: Which of the following is the BEST candidate for a three-poi...
Question 152: What is the purpose of the WBS?...
Question 153: You are a project manager working on a software development ...
Question 154: Because communications planning often is linked tightly with...
Question 155: The first deliverables from a project are ready, and the pro...
Question 156: Which enterprise environmental factors are considered during...
Question 157: The team is in the process of validating that the quality pl...
Question 158: Crosswind Custom Homes is building a customer's dream house....
Question 159: Which of the following is NOT a valid reason to authorize a ...
Question 160: While working on a project, the project manager realizes tha...
Question 161: An input required in Define Scope is an organizational:...
Question 162: During the execution phase of a large project there is an ex...
Question 163: Diagram: (Exhibit) If the imposed finish time in question 3 ...
Question 164: Which earned value management (EVM) metric is a measure of t...
Question 165: Tools and techniques used in Direct and Manage Project Work ...
Question 166: A project manager is managing multiple teams. One team membe...
Question 167: You are a project manager and you are in the closing phase. ...
Question 168: Those who enter into a contractual agreement to provide serv...
Question 169: Your role in the project includes helping to resolve problem...
Question 170: In an organization with good work-life balance, one team was...
Question 171: While preparing a project charter for a new project, a proje...
Question 172: The contract type that often spans multiple years and allows...
Question 173: During a project's third iteration, two of the existing team...
Question 174: You are managing a software project. You are partway through...
Question 175: A project team conducts acceptance testing of equipment agai...
Question 176: A summary WBS is usually developed in the...
Question 177: You have been assigned as the project manager for a major pr...
Question 178: A project manager is leading a project that is in an advance...
Question 179: How is quality control performed?...
Question 180: The process of defining how the project scope will be valida...
Question 181: In project management, Work authorization is normally not......
Question 182: A project has closed, and the project manager moves on to a ...
Question 183: Contested changes are requested changes when the buyer and s...
Question 184: You are managing a design project. You find that bringing al...
Question 185: Although the project charter serves to state the project man...
1 commentQuestion 186: A project manager has received an updated earned value analy...
Question 187: The team of Project Managers works in their company with a v...
Question 188: You are trying to determine whether or not to conduct 100% f...
Question 189: Which of the following depicts a hierarchical tabulation of ...
Question 190: _____ is a receipt issued by a carrier for merchandise to be...
Question 191: schedule overruns A project manager is just finishing up a p...
Question 192: Which process involves aggregating the estimated costs of th...
Question 193: Which process documents the business needs of a project and ...
Question 194: A company is about to fund a new project to develop a produc...
Question 195: An organization has contracts with an external supplier to s...
Question 196: Earned value measurement is an example of:...
Question 197: A project manager has been assigned to complete a worksite p...
Question 198: Crosswind Custom Homes is building a customer's dream house....
Question 199: A project deadline is fast approaching, and the team suggest...
Question 200: Which of the following theories are illustrated by the princ...
Question 201: Which of the following is an example of the simplest fixed-p...
Question 202: The outcome that must be produced to complete a part of a pr...
Question 203: After a meeting with the customer, the project manager recei...
Question 204: The project manager is experiencing delays with two critical...
Question 205: As a PMP, one of your responsibilities is to ensure integrit...
Question 206: Which is the correct formula for calculating expected activi...
Question 207: Who is responsible for issuing the project charter?...
Question 208: A project team member identifies a quality issue that may ca...
Question 209: A project manager has outsourced a critical programming task...
Question 210: Taking the following table into account, where would correct...
Question 211: An organization's management system is being upgraded by an ...
Question 212: For a stakeholder with low interest and high power, the proj...
Question 213: A leadership style in which the project manager shares probl...
Question 214: All the following statements regarding critical chain method...
Question 215: The following individuals are responsible for determining th...
Question 216: One team member is not as active as the rest of the team dur...
Question 217: Which of the following is a tool for analyzing a design, det...
Question 218: Which of the following scheduling techniques focuses on mana...
Question 219: An organization is transitioning to an agile approach. At th...
Question 220: You are working on a project that needs approval from your C...
Question 221: The process of identifying and documenting the specific acti...
Question 222: The sponsor plays a key role in project success. Which of th...
Question 223: A new project manager for an agile project is reviewing with...
Question 224: Plan-do-check-act is also known as:...
Question 225: A project manager is leading a project that is implementing ...
1 commentQuestion 226: Part of being a project manager involves dealing with confli...
Question 227: The utility of a risk seeker is:...
Question 228: While identifying risks for a new construction project, you ...
Question 229: Quantitative assessment(s) of the likely costs of the resour...
Question 230: An output of scope definition is:...
1 commentQuestion 231: A project manager is working on a project to create a new so...