<< Prev Question Next Question >>

Question 128/231

Labor, materials, equipment, and supplies are examples of:

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (231q)
Question 1: During a review meeting, the project manager realizes that s...
Question 2: The Project Management Process Group in which performance is...
1 commentQuestion 3: During a project review meeting, stakeholder A points out th...
Question 4: During the retrospective ceremony, the agile team is talking...
Question 5: A project has been long and difficult. The team is relieved ...
Question 6: A comprehensive definition of scope management would be:...
Question 7: The work that must be done in order to deliver a product wit...
Question 8: The process of identifying specific actions to be performed ...
Question 9: The ISO 9000 standards provide______________...
Question 10: An issue log is an input to which Project Human Resource Man...
Question 11: Drag the organizational characteristics on the left to the c...
Question 12: You are in the process of purchasing 67 desktop computers, m...
Question 13: During implementation of the delivery as defined in the proj...
Question 14: During which phase of the project lifecycle is the level of ...
Question 15: A project manager is receiving conflicting requirements from...
Question 16: You are the project manager on a project to improve traffic ...
Question 17: A project manager has been assigned to a new project. During...
Question 18: A prefects key stakeholder resigns and a new one is selected...
Question 19: During the daily standup meeting that is assessing progress ...
1 commentQuestion 20: A project is on its sixth iteration out of seven. Select the...
1 commentQuestion 21: Based on the following table, what is the total float for ac...
Question 22: Conditions that are not under the control of the project tea...
Question 23: You are a contract project manager within an information tec...
Question 24: There is a project with CPI = 0.81 and TCPI = 1.00001; this ...
Question 25: A project manager is initiating a highly controversial proje...
Question 26: Assume that your actual costs are $1,000; your planned value...
Question 27: The Project Manager is working with the customer to gain for...
Question 28: When comparing the cost of competing projects, which of the ...
Question 29: You have been hired as a project manager for a small local b...
Question 30: A project manager in a large government agency is implementi...
Question 31: A large corporation completed a corporate social responsibil...
Question 32: After numerous meetings, the project manager was unable to o...
Question 33: The project manager has recently received funding approval f...
Question 34: Which of the following project communication management proc...
Question 35: You are in the process of defining how to plan and execute t...
Question 36: Management decision-making includes:...
Question 37: A project manager at a company is considering a high-perform...
Question 38: A construction project to build a fish hatchery is in execut...
Question 39: Which is not an activity included in the Integrated change c...
Question 40: Units of measure, level of precision, level of accuracy, con...
Question 41: Drag the characteristics of the stage on the left to the cor...
Question 42: Risk mitigation involves______________...
Question 43: A project manager learns that the team can implement a minor...
Question 44: The Plan Stakeholder Management process belongs to which Pro...
Question 45: 80% of the problems are found in 20% of the work is a concep...
Question 46: In the phase sequence defined by project life cycles, a phas...
Question 47: A project must be simultaneously implemented in two countrie...
Question 48: A series of consecutive points on the same side of the avera...
Question 49: The ISO 9000 standards provide______________...
Question 50: The Project Manager is in the process of planning the projec...
Question 51: A team receives outsourced deliverables and determines that ...
Question 52: An intern is replacing a critical resource midway through a ...
Question 53: A project manager has been asked to participate in the procu...
Question 54: In which of the following types of organizational structures...
Question 55: The most common communication problem during negotiations is...
Question 56: In your software project, you have a programmer who constant...
Question 57: Drag the interpersonal skill on the left to the correct scen...
Question 58: An employee approaches you and asks to tell you something in...
Question 59: Which of the following is not a scope management process?...
Question 60: A project manager is assigned to a new project. Many of the ...
Question 61: Integrated change control includes the following activities ...
Question 62: Requirements for formal contract acceptance and closure usua...
Question 63: Which is the Estimate Costs technique used most frequently i...
Question 64: Your stakeholders have asked for an analysis of the cost ris...
Question 65: A project was assessed and the following Earned value data h...
Question 66: An example of coercive power would be:...
Question 67: The stakeholders on a new compliance project request a deliv...
Question 68: You are a contract project manager for a wholesale flower di...
Question 69: Which of the following factors is lowest at the start of the...
1 commentQuestion 70: A project manager notices an unusually high rate of risks, b...
Question 71: During a project's execution phase, the project manager rece...
Question 72: Which of the following is a tool for analyzing a design, det...
Question 73: Which of the following statement are false?...
Question 74: A project is sponsored by the client's chief technology offi...
Question 75: Which of the following is an input of the Define Activities ...
Question 76: (Exhibit) Based on the project scheduled, how much float is ...
Question 77: In what knowledge area does Activity Resource Estimating occ...
Question 78: Which quality management and control tool is useful in visua...
Question 79: Early in a project, a team member failed to effectively comm...
Question 80: Which of the following is true regarding product scope descr...
Question 81: You are the project manager responsible for constructing new...
Question 82: A vendor who supplied material that failed to meet a technic...
Question 83: While browsing a local archive, a new project manager finds ...
Question 84: Which of the following is CORRECT about quality improvements...
Question 85: The lowest level normally depicted in a work breakdown struc...
Question 86: Your selection committee is debating between two projects. P...
Question 87: The profitability and technical data studies are provided in...
Question 88: Assume you are beginning your project to develop a series of...
Question 89: You monitored figures on cost and planned/earned value for e...
Question 90: Your project has been under way for some time, but indicator...
Question 91: You are managing a software development project. One of your...
Question 92: A number of organizational process assets are useful as inpu...
1 commentQuestion 93: At the end of project execution, a project manager has retai...
Question 94: Working on your project management training curricula projec...
Question 95: Which type of management focuses on ensuring that projects a...
Question 96: In a project management team meeting, one of the team member...
Question 97: Alberto is the project manager of a software implementation ...
Question 98: Which statement describes best the purpose of brainstorming ...
Question 99: A project manager developed the scope management plan for a ...
Question 100: Which of the following is true about pure risk?...
Question 101: A project manager assumes a three-year, multiphase project w...
Question 102: Calculate the standard deviation for the following: Pessimis...
Question 103: Which type of analysis is used to develop the communications...
Question 104: A team has been working together for several months and has ...
Question 105: Each project can benefit from stakeholder involvement; howev...
1 commentQuestion 106: During the next monthly meeting, a project manager wants to ...
Question 107: At what stage of a project does the development of a cohesiv...
Question 108: Which process involves the creation of a document that provi...
Question 109: Tom is a project manager on an industrial design project. He...
Question 110: According to a new product development process, the marketin...
Question 111: You realize that on projects, some stakeholders will not be ...
Question 112: Obtaining information from prospective sellers on how projec...
Question 113: A project plan generally includes the following:...
Question 114: A project manager discusses a project's status with the cust...
Question 115: You are managing a project with an EV of $15,000, PV of $12,...
Question 116: During a project's planning session, the project team discus...
Question 117: The scope baseline/project charter is prepared by the:...
Question 118: The end point of a project phase can be referred to as:...
Question 119: The purpose of a numeric scale in risk management is to_____...
Question 120: The process of monitoring the status of the project to updat...
Question 121: During a project to create an organizational business plan, ...
Question 122: A project is delayed. The project manager added extra resour...
Question 123: Drag the interpersonal skill on the left to the correct scen...
Question 124: Which of the following are valid ways to breakdown the work ...
Question 125: You are currently in the process of prioritizing risks by th...
Question 126: You are in the process of controlling changes to the project...
Question 127: You have been assigned to a project to build a large 30-stor...
Question 128: Labor, materials, equipment, and supplies are examples of:...
Question 129: The project will be using a company to provide the technicia...
Question 130: After finishing the planning phase of a project, but before ...
Question 131: In Project Cost Management, which input is exclusive to the ...
Question 132: Create Procurement document is done in _______....
1 commentQuestion 133: In response to a delay, a project manager adds new resource ...
Question 134: You have a conflict on your team but have enough time to res...
Question 135: I luting project execution, a project manager identifies a m...
Question 136: Mark is a project manager working on a compliance project in...
Question 137: During the executing phase, a project manager is reviewing t...
Question 138: At the end of a meeting a functional manager takes the proje...
Question 139: A lessons learned is BEST completed by:...
Question 140: Respect is...
Question 141: Participative Management:
Question 142: Analogous Estimate Costs is _________....
Question 143: Which of the following is an input to Direct and Manage Proj...
Question 144: In your project, if earned value (EV) is larger than planned...
Question 145: The risk management plan is a subset of the project manageme...
Question 146: Project managers spend a great deal of time communicating wi...
Question 147: On your project, you need to assign costs to the time period...
Question 148: In your last project status meeting, you had 15 team members...
Question 149: You can use various estimating approaches to determine activ...
Question 150: The Project Manager has some issues on the team between two ...
Question 151: Which of the following is the BEST candidate for a three-poi...
Question 152: What is the purpose of the WBS?...
Question 153: You are a project manager working on a software development ...
Question 154: Because communications planning often is linked tightly with...
Question 155: The first deliverables from a project are ready, and the pro...
Question 156: Which enterprise environmental factors are considered during...
Question 157: The team is in the process of validating that the quality pl...
Question 158: Crosswind Custom Homes is building a customer's dream house....
Question 159: Which of the following is NOT a valid reason to authorize a ...
Question 160: While working on a project, the project manager realizes tha...
Question 161: An input required in Define Scope is an organizational:...
Question 162: During the execution phase of a large project there is an ex...
Question 163: Diagram: (Exhibit) If the imposed finish time in question 3 ...
Question 164: Which earned value management (EVM) metric is a measure of t...
Question 165: Tools and techniques used in Direct and Manage Project Work ...
Question 166: A project manager is managing multiple teams. One team membe...
Question 167: You are a project manager and you are in the closing phase. ...
Question 168: Those who enter into a contractual agreement to provide serv...
Question 169: Your role in the project includes helping to resolve problem...
Question 170: In an organization with good work-life balance, one team was...
Question 171: While preparing a project charter for a new project, a proje...
Question 172: The contract type that often spans multiple years and allows...
Question 173: During a project's third iteration, two of the existing team...
Question 174: You are managing a software project. You are partway through...
Question 175: A project team conducts acceptance testing of equipment agai...
Question 176: A summary WBS is usually developed in the...
Question 177: You have been assigned as the project manager for a major pr...
Question 178: A project manager is leading a project that is in an advance...
Question 179: How is quality control performed?...
Question 180: The process of defining how the project scope will be valida...
Question 181: In project management, Work authorization is normally not......
Question 182: A project has closed, and the project manager moves on to a ...
Question 183: Contested changes are requested changes when the buyer and s...
Question 184: You are managing a design project. You find that bringing al...
Question 185: Although the project charter serves to state the project man...
1 commentQuestion 186: A project manager has received an updated earned value analy...
Question 187: The team of Project Managers works in their company with a v...
Question 188: You are trying to determine whether or not to conduct 100% f...
Question 189: Which of the following depicts a hierarchical tabulation of ...
Question 190: _____ is a receipt issued by a carrier for merchandise to be...
Question 191: schedule overruns A project manager is just finishing up a p...
Question 192: Which process involves aggregating the estimated costs of th...
Question 193: Which process documents the business needs of a project and ...
Question 194: A company is about to fund a new project to develop a produc...
Question 195: An organization has contracts with an external supplier to s...
Question 196: Earned value measurement is an example of:...
Question 197: A project manager has been assigned to complete a worksite p...
Question 198: Crosswind Custom Homes is building a customer's dream house....
Question 199: A project deadline is fast approaching, and the team suggest...
Question 200: Which of the following theories are illustrated by the princ...
Question 201: Which of the following is an example of the simplest fixed-p...
Question 202: The outcome that must be produced to complete a part of a pr...
Question 203: After a meeting with the customer, the project manager recei...
Question 204: The project manager is experiencing delays with two critical...
Question 205: As a PMP, one of your responsibilities is to ensure integrit...
Question 206: Which is the correct formula for calculating expected activi...
Question 207: Who is responsible for issuing the project charter?...
Question 208: A project team member identifies a quality issue that may ca...
Question 209: A project manager has outsourced a critical programming task...
Question 210: Taking the following table into account, where would correct...
Question 211: An organization's management system is being upgraded by an ...
Question 212: For a stakeholder with low interest and high power, the proj...
Question 213: A leadership style in which the project manager shares probl...
Question 214: All the following statements regarding critical chain method...
Question 215: The following individuals are responsible for determining th...
Question 216: One team member is not as active as the rest of the team dur...
Question 217: Which of the following is a tool for analyzing a design, det...
Question 218: Which of the following scheduling techniques focuses on mana...
Question 219: An organization is transitioning to an agile approach. At th...
Question 220: You are working on a project that needs approval from your C...
Question 221: The process of identifying and documenting the specific acti...
Question 222: The sponsor plays a key role in project success. Which of th...
Question 223: A new project manager for an agile project is reviewing with...
Question 224: Plan-do-check-act is also known as:...
Question 225: A project manager is leading a project that is implementing ...
1 commentQuestion 226: Part of being a project manager involves dealing with confli...
Question 227: The utility of a risk seeker is:...
Question 228: While identifying risks for a new construction project, you ...
Question 229: Quantitative assessment(s) of the likely costs of the resour...
Question 230: An output of scope definition is:...
Question 231: A project manager is working on a project to create a new so...