You are a project manager working with a cross-functional project team. The project spans multiple years
and has 25000 activities owned across these cross-functional teams. The team leads for the functional
teams do not want to view activities outside of the ones that they own.
They have asked you to find a way for them to only see their activities.
Identify three P6 EPPM features that would help you respond to this requirement.