Valid 1z0-567 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-567 Exam! ExamDiscuss.com now offer the newest 1z0-567 exam dumps, the ExamDiscuss.com 1z0-567 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-567 dumps with Test Engine here:
An activity is to be completed within a fixed time period and the total effort is also fixed. What duration type should be used?
Correct Answer: D
Explanation/Reference: For Fixed Duration & Units, the duration and units remain constant as the units/time are changed. Use this duration type when the activity must be completed within a fixed time period and the total amount of work is fixed. Incorrect answers: A: Fixed Units - Used when costs/work effort is a limiting factor. Use this duration type when the total amount of work (costs or units) is fixed, and increasing resources can decrease the duration. In this case, if you update the duration or units/time, the units remain constant.