Explanation/Reference:
Response Plan row: Create one or more response plans while you are in the planning phase and indicate
the response type. When you have analyzed your response options, choose one response plan by
selecting the Active option next to the appropriate response plan.
In the example below, two response plans have been created for the Concrete supply constrained risk.
The first plan is to accept the risk and take no action; the second plan is to reduce the impact of the risk by
contracting with alternative suppliers. You can see this second plan was selected as the plan of choice.

Note:
* A risk register and risk scoring matrix provide a system for monitoring and tracking risks.
* Rather than having a single response, you can create multiple responses to a risk.
* Once you have established your risks, you can view the Probability and Impact Diagram, which shows
how the risks are coded. Several pre-defined PID matrices have been provided from which we can choose.

Reference: Oracle Primavera P6, Working with Risk Response Plans