Explanation/Reference:
Example of Capacity Planning chart:

Frame B is the top-right quarter of the Capacity Planning screen. This is the Gantt area where projects
are represented using scheduled dates on the green bar. The orange bar is only seen in P6 on this screen
and represents the forecast. The forecast bar will be the same as the schedule/current dates bar unless
forecast dates are specifically used (which is not typical). The purpose of the two bars is best used when
viewing bids or projects in the future.
Note:
Using the Chart tab, users can change the Capacity Planning view to show Units or Costs in the Gantt
chart, and can choose to display either only projects selected or the entire portfolio. Other adjustments can
be made here to create a desired view.