Valid 1Z0-902 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-902 Exam! ExamDiscuss.com now offer the newest 1Z0-902 exam dumps, the ExamDiscuss.com 1Z0-902 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-902 dumps with Test Engine here:
You are providing oversight for the delivery of a new Exadata Database Machine. 1. Stabilize the Exadata Rack. 2. Unpack Oracle Exadata Rack. 3. Review the safety guidelines. 4. Let the Exadata acclimatize for 24 hours. 5. Power on Exadata PDU A. 6. Place Exadata in its allocated space. 7. Power on Exadata PDU B. What is the correct order of these steps?
Correct Answer: C
This ordering is based on the Oracle Exadata Database Machine X9M Implementation Essentials Official Text Book and other resources. First, the Exadata should be stabilized and unpacked (Steps 2 and 3). Then, the safety guidelines should be reviewed (Step 4). The Exadata should then be allowed to acclimatize for 24 hours (Step 4). After that, the Exadata PDU A should be powered on (Step 6) and the Exadata should be placed in its allocated space (Step 6). Finally, the Exadata PDU B should be powered on (Step 7).