Valid 1Z0-902 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-902 Exam! ExamDiscuss.com now offer the newest 1Z0-902 exam dumps, the ExamDiscuss.com 1Z0-902 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-902 dumps with Test Engine here:
A new Exadata Quarter Rack with 2 Database Servers and 3 HC Storage Servers and 3-phase 15kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU. Which statement is correct?
Correct Answer: B
An Exadata Quarter Rack with 2 Database Servers and 3 HC Storage Servers and 3-phase 15kVA PDUs would typically require two power feeds per PDU, one for each of the two power distribution units (PDUs) in the rack. A single power feed per PDU is not sufficient to provide the necessary power to the servers and storage in the rack. The installation cannot proceed until two power feeds are available per PDU. According to the Oracle Exadata Database Machine X9M Implementation Essentials Official Text Book [1][2], it is recommended that each PDU should have at least two power feeds from different power sources in the data center. This is to ensure redundancy and avoid any power interruption due to power failure on one of the power sources. Splitter cables are not recommended, as they can reduce efficiency and increase the risk of overheating. Rearranging the power cables within the rack is not recommended either, as it does not provide the necessary redundancy for the PDU.