Valid Project-Management Dumps shared by EduDump.com for Helping Passing Project-Management Exam! EduDump.com now offer the newest Project-Management exam dumps, the EduDump.com Project-Management exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Management dumps with Test Engine here:
Which four factors will most affect the choice of project delivery method? Check the four that apply.
Correct Answer: A,C,E,F
A). Project scope: Impacts complexity and integration needs. C). Owner capabilities: Determines whether the owner can manage multiple contracts (as in DBB or CM). E). Risk tolerance: Risk-averse owners may prefer DB or CM-at-risk with cost guarantees. F). Construction cost: Influences whether fast-tracking or GMP methods are needed. Incorrect: B). The firm's size is rarely a determining factor. D). Code compliance is required in all methods but doesn't drive delivery choice. References: AHPP Chapter 10 - Choosing a Delivery Method NCARB ARE 5.0 Handbook - Delivery Method Evaluation Criteria