Valid Project-Management Dumps shared by EduDump.com for Helping Passing Project-Management Exam! EduDump.com now offer the newest Project-Management exam dumps, the EduDump.com Project-Management exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Management dumps with Test Engine here:
The owner and architect sign a Basic Services Agreement for the design of a museum. Based on AIA Document B101-2017, Owner and Architect Agreement, which line items should be excluded from the architect's cost estimate? Check the two that apply.
Correct Answer: C,E
Per AIA B101-2017 § 6.1, the "Cost of the Work" includes items designed or specified by the architect in the construction contract. FF&E and owner-provided landscape features (like plants, art, and loose furniture) are typically excluded, as these may be contracted separately by the owner or coordinated outside basic architectural services. References: AIA B101-2017 §§ 6.1-6.3 NCARB ARE 5.0 Handbook - PjM & PPD: Project Cost Estimating AHPP, Chapter 11: Cost Estimating Procedures