Valid Project-Management Dumps shared by EduDump.com for Helping Passing Project-Management Exam! EduDump.com now offer the newest Project-Management exam dumps, the EduDump.com Project-Management exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Management dumps with Test Engine here:
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?
Correct Answer: B
An RFI is a formal request from the contractor for clarification regarding the contract documents during construction. The architect's primary responsibility is to respond clearly and promptly to avoid project delays and confusion. The architect reviews the question, interprets the design intent, and provides necessary clarifications or directs the contractor accordingly. While an RFI can lead to change orders, issuing them is a separate process involving owner approval. The architect's role focuses on maintaining project momentum and communication flow. This aligns with the ARE 5.0 PjM emphasis on construction phase communication, contractor coordination, and proper documentation of clarifications as part of contract administration.